Work done by SUDA in the year 2006-2007.
|
| No. |
Description |
Price (in lacs) |
Note |
|
| 1. |
Water Supply Project:
1. Constructed Over Head Tank (Capacity
5 lakh ltrs.) at Vesu & Pal.
|
113.58 |
Work is completed. |
|
| 2. |
Roads:
| 1. |
Completed approx. 90 Km. length
TP/DP Roads in SUDA area.
|
|
2200.00 |
Work is completed. |
|
| |
| 2. |
Construction of Valthan Puna Canal
Road.
|
|
830.00 |
Work is in progress.
Total project Cost @
Rs. 1100 lacs. |
|
| 3. |
Bridges:
| 1. |
Bridge connecting Sarthana - Simada
across Khadi on 30 Mt. wide Road.
|
|
132.44 |
Work is completed. |
|
| |
| 2. |
Bridge near Haripura across Khadi.
|
|
111.86 |
Work is in Progress.
|
|
| |
| 3. |
Bridge connecting Sarthana - Simada
across Khadi on 18 mt. wide Road.
|
|
81.38 |
Work is in progress. |
|
| 4. |
Street Light:
| 1. |
Street Lights on Sarthana Jakatnaka to
Kamrej Char Rasta with Public
Participation.
|
|
70.00
|
Work is in progress.
|
|
|
| 2. |
Street Lights & Tree Plantation on Un-
Navsari Road 2 Km. Length with
Public Participation.
|
|
58.00
|
Work is completed.
|
|
| 5. |
Environment:
Provided Tree Guard for Tree Plantation in
SUDA area.
|
7.55 |
Tree Plantation using
Tree Guard has been
done by Gram
Panchayat. |
|
| 6. |
Cleanliness::
SUDA has provided Dustbins, Hand Carts
etc. for cleanliness work.
|
8.00 |
Dustbins & Hand Carts
are used for disposal of
sewage in SUDA area
by Gram Panchayat. |
|
| 7. |
Flood - 2006.
Suda had worked hard and assisted SMC
for relief works after unprecedented flood
in Surat in August, 2006. Attended lowest
area of the city round the clock day and
night for a week in Kadarshah ni Nal
where flood water entered first and
receded last during floods and many
other duties given by Chief Co-ordinator.
Got appreciation letters from Gujarat
State Collector, Principal Secretary and
Chief Co-ordinator Gujarat State for
rescue, relief and rehabilitation.
|
|
|
|
|
Work done by SUDA in the year 2005-2006.
|
| No. |
Description |
Price (in lacs) |
Note |
|
| 1. |
Housing Project:
Constructed 286 LIG Quarters (Two Room +
Kitchen) under Honorable Chief Minister's
"20 Points" programme at Vesu.
|
560.00 |
Work is completed and
allotted to the
beneficiaries. |
|
| 2. |
Roads:
| 1. |
Completed 30 Km. length TP/DP Roads
in SUDA area. |
|
732.00 |
Work is completed. |
|
| |
| 2. |
Two Lanes Valthan Puna Canal Road. |
|
1100.00 |
Work started in
November, 2005.
Total Project cost @
Rs. 1100 lacs. |
|
| |
Udhana - Magdalla, Surat - Dumas, Un-
Navsari Roads
|
490.00 |
Work is completed.
Grant to R & B Dept. |
|
| 3. |
Bridges:
| 1. |
4 Lanes Bridge on Khadi near Mahavir
Jakatnaka. |
|
135.00 |
Work is completed. |
|
| |
| 2. |
4 Lanes Bridge at Nana Varachha 30%
share to SMC. |
|
63.00 |
3.Work is completed.
Total share paid by
SUDA
Rs. 763 lacs. |
|
| |
| 3. |
4 Lane Kakrakhadi Bridge
50% partnership with SMC. |
|
425.00 |
Work is completed. |
|
| 4. |
Water Supply Project:
| 1. |
Pumping Stations at Vesu & Pal. |
| 2. |
Approx. 60 km. pipeline network in 14
TP Schemes of Vesu & Pal area of
SUDA. |
|
1245.28 |
Work is in progress.
Total Project cost @
Rs. 2670 lacs. |
|
| 5. |
Sewage:
3 MLD Sewage Pumping Station at Amroli -
Chhaprabhata Khadi.
|
70.00 |
Work is in progress.
Work is completed and
handed over to SMC. |
|
| 6. |
Environment:
Provided Tree Guards for plantation in SUDA
Area.
|
10.00 |
Provided to Gram Panchayat |
|
| 7. |
Cleanliness:
Provided Dustbins, Hand Carts, and Garbage
Carts in different areas of SUDA.
|
10.00 |
Provided to Gram Panchayat |
|
|
|
|
Work done by SUDA in the year 2004-2005.
|
| No. |
Description |
Price (in lacs) |
Note |
|
| 1. |
Housing Project:
Constructed 112 LIG Quarters (Two
Room + Kitchen) under Honorable Chief
Minister's "20 Points" programme at
Vesu.
|
180.00 |
Work is completed
and allotted to the
beneficiaries. |
|
| 2. |
Roads:
Completed 15 Km. length TP/DP Roads
in SUDA area.
|
400.00 |
Work is completed. |
|
| 3. |
Water Supply Project:
| 1. |
Pumping Stations at Vesu & Pal. |
| 1. |
Approx. 60 km. pipeline network in
14 TP Schemes of Vesu & Pal area of
SUDA. |
|
1200.00 |
work started in
May-2004
Total Project cost
Rs. 2670 lacs. |
|
| 4. |
Environment:
Provided Tree Guards for plantation in
SUDA Area.
|
7.80 |
Provided to Gram
Panchayat. |
|
| 5. |
Cleanliness:
Provided Dustbins, Hand Carts, and
Garbage Carts in different areas of
SUDA.
|
7.83 |
Work done in Gram
Panchayat |
|
|
|
|
|
Work done by SUDA in the year 2003-2004.
| No. |
Description |
Price (in lacs) |
Note |
|
| 1. |
Residential Scheme According to honorable chief minister's "20 Mudda Programme" At : vesu FinalPlot No: 168 TPscheme no: 1 ,Construct 182 L I G residence. |
285.00 |
selling prize: 1,71,000/- each residence work is progress |
|
| 2. |
E. W. S residence At: pal Final Plot No: 184 TP scheme: (10) 100 residence |
62.00 |
working will be start on june-2004 |
|
| 3. |
Under the mission of Connecting main roads of surat city remove the illegal property on road of Un-Sachin road and wide it 6 mit. Length: 1350 mit. |
20.00 |
work in progress |
|
| 4. |
Development of Roads : 1. develop the Ringroad and Linking road Leangth: 23.00 k.m. 2. Roads of TP scheme Leangth: 10.00 k.m. |
300.00 |
working will be start on may-2004 |
|
| 5. |
At Bhatar : Development of Highrise Comercial Complex T P Scheme No: 28 S.N :5 Area:1906 sq.mt |
200.00 |
working will be start on june-2004 |
|
| 6. |
Computerization of office under E-Governance project |
20.00 |
working will be start from 1st may 2004 |
|
| 7. |
Plan to Bridge on Anjali Khadi At:puna |
10.00 |
work completed |
|
|
Drainage Managment |
|
| A. |
Enviro Control Associates sewage Treatment Plant-22.00 MLD At six villages : Amaroli,Kosad,Chhaprabhatha , Variyav,Ganeshpura Utran |
2200.00 |
According to 2011 population strength |
|
| B. |
At :Vesu TP:8 develop the planning of drainage system: Consultant:Polution Control Engg. Final Sewage Disposal Capasity: 22.00 MLD. Development is working on Base of phases |
410.00 |
Prepare tha report according to the population of year:2033 Expected expenses : Rs 3787 lacs |
|
| C. |
At :Pal-Palanpor TP:6 develop the planning of drainage system: Consultant:Polution Control Engg. Final Sewage Disposal Capasity: 66.00 MLD. Development is working on Base of phases during the Phase I axpected expence |
350.00 |
Prepare tha report according to the population of year:2033 Expected expenses : Rs 2401 lacs |
|
| D. |
At :Puna Area TP:4 develop the planning of drainage system: Consultant : Stpathi Disigner and consultant Pvt.Ltd. surveying procedure is in progress |
|
surveying procedure is in progress |
|
|
Water Supply: |
|
| A. |
Arrange the water supply facility At; TP scheme: 8 . Consultant: polution Control Engg. Emergancy Need : 15.00 MLD |
900.00 |
Disscution with SMC to take the water strenght at one point for comromizing rate |
|
| B. |
Arrange the water supply facility At;Palnpor Area TP scheme: 6 . Consultant: polution Control Engg. Emergancy Need : 10.00 MLD |
750.00 |
same as above |
|
Storm Water Management |
|
|
|
To give the Advertize in to newspaper for creat Projectreport on Rainy water gutter management At: Vesu area TP Scheme . offer for consultant |
2000.00 |
working will start on project january 2004 |
|
|
|
|
|
|
Work done by SUDA in the year 2002-2003.
| No. |
Description |
Price (in lacs) |
|
| 1. |
E.W.S - Residential Scheme According to honorable Chief minister's "15 Mudda Programme". |
600.00 |
|
| 2. |
New RCC Port Develop new jetty besides the present jetty at Dumas. |
12.00 |
|
| 3. |
Bridge on Anjali Khadi at Puna Joint venture with SMC - Bridge built on Anjali khadi joining Karanj of SMC area and Puna of Suda area. |
Total: 40.00 Suda's Contribution: 20.00 |
|
| 4. |
Street Light Street light on Amroli and Chhabrabhatha. |
7.00 |
|
| 5. |
Environment protection 3500 tree guards for Tree plantations |
5.00 |
|
| 6. |
Health Protection Cleaning drainage using JCB and provision of dustbin. |
6.50 |
|
| 7. |
Roads for D.P and T.P Total 14.00 kms length road for T.P and main roads of villages. |
115.00 |
|
| 8. |
T.P Schemes T.P scheme no. 1 for Vesu is accepted and T.P. 2,7,10,3 are in progress. |
|
|
|
|
|
|
|
| The Projects in Pipeline |
|
|
|
1 |
|
Corporate Office Building:
The project is under planning stage. The plan of the office building is approved
by Competent Authority. The office building is to be constructed in TP
Scheme No. 3, FP No. 78 having land area of 5000 Sq. m. at the cost of Rs. 800
lacs.
|
|
2 |
|
Construction of ROBs:
SUDA has proposed to construct ROBs at Sachin - Magdalla Road by widening
the existing ROB considering the heavy traffic, and new ROB at Gothan and
Sachin - Talangpur Road. Total costing of all ROB Rs. 5400.00 lacs. The
ROBs on Sachin - Magdalla Road and Gothan are approved under JNNURM
|
|
3 |
|
Lake Development:
SUDA has prepared the DPR for Lake Development costing Rs. 20 crores. The
total area of the project is 24 hectors (Six Villages). The DPR is submitted for
approval to Delhi under JNNURM Scheme.
(a) Talangpur
(b) Bhatiya
(c) Umbhel
(d) Bhesan
(e) Balkas
(f) Deladva
|
|
4 |
|
Bridges:
Two Lane Bridge joining Abhava - Ubhrat having 1800 m. length on Mindhola
river is proposed by SUDA. The preliminary works such as survey, soil
investigation are taken up. The estimated cost of the project is Rs. 30 crores.
This will facilitate in reducing the distance to Ubhrat by 20 km. Ubhrat is
having a Sea-Shore and famous for tourist place.
|
|
5 |
|
Outer Ring Road:
The Outer Ring Road of 6 lanes having 66 km length and 90 m. width is
proposed. This will help the diversion of traffic and thereby reducing the traffic
intensity on city area. The estimated cost of the project is Rs. 5000 lacs.
|
|
|
|
|
|